Activity Durations in MS-Project 2007







Microsoft Project 2007 supports input of Activity durations in a number of formats like Minutes, Hours, Days, Weeks and Months.

Under each Category, MS-Project allows the following two formats of entry
1. Duration – entered as hrs, days, wks, mons
2. Elapsed Duration – entered as ehrs, edays, ewks, emons

To understand how MS-Project uses each of these durations for schedule calculations we need to look at the following 2 calendar settings.

A. Project Calendar - To view the Project Calendar setting select Tools ->Change working Time
The settings used in the example case are the default MS-Project Standard Calendar.
Sunday & Saturday - Non working day
Monday to Friday - 8 Hrs [8:00AM to 12:00PM & 1:00PM to 5:00PM]

B. Project Calendar Options Settings - To view the Project Calendar option setting select Tools -> Options ->Calendar Tab. The settings used in the example case are the default MS-Project settings.
Hours per day - 8
Hours per week - 40
Days per months - 20

MS-Project Calculation

Task 1
Entered duration: 24 hrs
Start Date: 02-Mar-2009 8:00AM. Start Date is equal to the “Project Start Date”
(02-Mar-2009 8:00AM) since there is no predecessor assigned)
Finish Date: Start Date + 24 Working Hrs = 04-Mar-2009 5:00PM; 8 Hrs (02-Mar 8AM to 5PM) +
8 Hrs (03-Mar 8AM to 5PM) + 8 Hrs (04-Mar 8AM to 5PM)

Task 2
Entered duration: 24 ehrs
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 24 Hrs = 03-Mar-2009 8:00AM; 24 Hrs (02-Mar 8AM to 03-Mar 8AM)

Task 3
Entered duration: 2 days
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 16 Working Hrs (2 x 8 “Hours per day” setting in Options Dialog) =
03-Mar-2009 5:00PM; 8 Hrs (02-Mar 8AM to 5PM) + 8 Hrs (03-Mar 8AM to 5PM)

Task 4
Entered duration: 2 edays
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 48 Hrs (2 x 24 Hours/day) = 04-Mar-2009 8:00AM; 24 Hrs (02-Mar 8AM to 03-Mar 8AM) + 24 Hrs (03-Mar 8AM to 04-Mar 8AM)

Task 5
Entered duration: 2 wks
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 80 Working Hrs (2 x 40 “Hours per week” setting in Options Dialog) =
13-Mar-2009 5:00PM

Task 6
Entered duration: 2 ewks
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 336 Hrs (2 x 7 day/week x 24 Hours/day) = 16-Mar-2009 8:00AM


Task 7
Entered duration: 2 mons
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 320 Working Hrs (2 x 20 “days per month” x 8 “Hours per day” setting
in Options Dialog) = 24-Apr-2009 5:00PM

Task 8
Entered duration: 2 emons
Start Date: 02-Mar-2009 8:00AM equal to “Project Start Date”
Finish Date: Start Date + 1440 Hrs (2 x 30 day per month* x 24 Hours per day) =
01-May-2009 8:00AM
* MS-Project calculation engine assumes a fixed 30days per month factor for calculating durations entered as “emons”, hence verify whether the schedule output is in line with real life situation when using emons.